Notice is hereby given that Pembrokeshire Coastal Forum CIC has applied to Natural Resources Wales (“NRW”) for a marine licence variation to carry out a regulated activity under the Marine and Coastal Act 2009. The project requires EIA consent and is subject to the requirement for an environmental impact assessment (“EIA”) under the Marine Works (Environmental Impact Assessment) Regulations 2007 (“the EIA Regulations”). An environmental statement addendum has been prepared by the applicant.
The application is to vary some of the project parameters at the Warrior Way and Dale Roads offshore marine energy test sites, in proximity to Pembroke Dock; to facilitate the testing and development of marine energy projects.
Copies of the environmental statement addendum and other documents required by the EIA Regulations are available online from our public register.
You can search for the documents using the application reference number ORML1957v2.